Project Name Williamson Farms Phase 5
Project Location Edwardsville, KS
Completion Date June 2003
Estimated Cost for Entire Project $950,000
Estimated Cost for Work Which Firm was/is Responsible $950,000
Scope of Entire Project This project involves land planning for a 20 acre residential subdivision in Edwardsville.
Nature of responsibility in project
  • Street Layout, Intersection Improvements
  • Storm Water Study
  • Detention Basin Plans
  • Storm Water System
  • Sanitary Sewer
  • Water Line
  • Street Lighting
  • Personnel who worked on project Trent Robinett, Project Manager, Project Engineer